GB-Leeds: Design, Manufacture & Installation of Humidification Control to Air Handling Units 4, 5 & 7

Competitive Contract Notice

1. Title: GB-Leeds: Design, Manufacture & Installation of Humidification Control to Air Handling Units 4, 5 & 7
2. Awarding Authority:
Royal Armouries
Armouries Drive, Leeds, LS10 1LT, United Kingdom
Tel. 0113 220 1946, Email: procurement@armouries.org.uk, URL: https://royalarmouries.org/
Contact: Procurement Department, Attn: Katia Giovannini
3. Contract Type: Services
Sub Type: Other services.

4. Description: Cooling and ventilation equipment. Ventilation and air-conditioning installation work. Inspection of ventilation system. Ventilation consultancy services. Royal Armouries wishes to appoint a company to undertake a survey of its air handling units (AHU's) 4, 5 and 7, design, install and commission humidification controls capable of achieving control parameters specified. Interface to the Museum's Building Management System will be critical to ensure control.
5. CPV Codes:
42500000 - Cooling and ventilation equipment.
45331200 - Ventilation and air-conditioning installation work.
71315410 - Inspection of ventilation system.
71321400 - Ventilation consultancy services.

6. NUTS Codes :
UKE42 - Leeds

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: Leeds,
8. Reference Attributed by the Awarding Authority: RA-0152
9. Estimated Value of Requirement: Category I: 50K to 100K
Currency: GBP
10. Deadline for Expression of Interest: 21/09/2018 12:00:00
11. Address to which they must be sent:
Royal Armouries
Armouries Drive, Leeds, LS10 1LT, United Kingdom
Tel. 0113 220 1946, Email: procurement@armouries.org.uk, URL: https://royalarmouries.org/
Contact: Procurement Department, Attn: Katia Giovannini

12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
Full tender documentation will be released post the deadline set for the expressions of interest.
Attending a site visit prior to tender is a mandatory requirement. Tenderers will have the opportunity to attend a site visit on the following dates:
1. on Thursday 04 October at hrs.14:00
2. on Friday 05 October at hrs.14:00
For more information about this opportunity, please visit the Delta eSourcing portal at:
https://neupc.delta-esourcing.com/tenders/UK-GB-Leeds:-Design%2C-Manufacture-%26-Installation-of-Humidification-Control-to-Air-Handling-Units-4%2C-5-%26-7/P8K4K353A6

To respond to this opportunity, please click here:
https://neupc.delta-esourcing.com/respond/P8K4K353A6
TKR-2018831-PRO-13113565
Suitable for VCO: No
Procedure Type:OPEN
Period of Work Start date: 15/11/2018
Period of Work End date: 19/01/2019
Is this a Framework Agreement?: no